Calendar Table

The software lets you work on several calendars: each work center or each machine can use a particular calendar.

A calendar contains day by day work periods (shifts) defined by a starting hour and a duration expressed in standard hours.

Calendars are necessary to perform infinite scheduling, finite scheduling and work load calculations..

The Plant Calendar (PC) code is automatically created. However, its working periods must be created by the calendar maintenance function. It can not be deleted.

A calendar code must be specified for each work center, for each machine and for the resource items.