At the end of the net requirements computation procedure, a planning report is edited. It can be printed by clicking on the Print button. This report displays the selected planning options.
In case of problems during the computation, specific information is displayed. These messages are the following:
Impossible to place within the lead-time: the WO or the PR cannot be generated within the lead-time as it must be started before the current date.
No release routing: no release routing has been specified for the item (Routings table, Item window).
No valid release routing: the release routing is not valid at the WO release date.
Needs not covered at the required date: due to excessive lead-times, it is not possible to generate WO/PR in order to meet the needs.
Delete WO/PR xxx: there is not firm need corresponding to the WO or the PR.