Work Center Queue Profile

In the upper window, this function shows the evolution, along time, of the work load in queue, calculated by work center. The description of the work center utilization is depicted in the lower window.

First a work center must be selected from the work center list.

Then, the units and number of units of time to display can be chosen. The All option shows the queue for the whole scheduling time horizon.

The buttons >> and << allow the display to scroll. The Calendar button makes it easy to get to the desired date.

The Print button starts printing the current page.

The Events button shows the chronological list of events for each work center. The events are represented by a code (see the shop event history for the meaning of these codes).

The Utilization button shows the detail of the machine utilization for each work center (see above Machine Utilization).