This load table cumulates the work loads corresponding to the planned orders, the firm orders and the open orders, during a period selected in days, in weeks or in months. These loads are either the labor loads or the machine loads.
It is possible to compute the loads corresponding to the forward schedule and to the backward schedule.
You choose the type of data you want to see in the drop-down list: work centers, cost centers, workshops, labor qualifications or tools. After the selection, you have to click on the Update button to calculate the loads.
The Graph button provides a visual synthesis of capacity utilizations.
By clicking on the left-hand column (i.e. the Total column), the work load graph for the selected entity is displayed.